A Summary of Washington State’s Updated Construction Crane Rule
Washington State’s new regulation for cranes and derricks in construction was released on August 5, 2025 and goes into effect on September 5, 2025. The rule had been in development since 2018 and included a number of stakeholder meetings from August 2023 through to April 2024 with public hearings held in May 2025.
The intent of the rule was to ensure that Washington States rules were at least as effective as OSHA as well as to address other areas in Chapter 296-155 WAC relating to cranes based on current industry practice or clarifying language to maintain safety and health protections for employees. The 243 page rule has a number of areas that are addressed which are summarized below:
OSHA Initiated Changes:
- Multipurpose equipment used as a crane
- Operator certification
- Operator evaluation
- Forklift when used as a crane
Washington State L&I Initiated Changes:
- Power line rule updates
- Tower crane assembly, disassembly, or reconfiguration
- Equipment with capacities of 2,000 pounds and under
- Crane certifier certification
- Crane certification worksheet/annual inspection
- Lift Director qualifications
- A/D Director qualifications
- A/D Director duties
- Rigger duties
- Site Supervisor duties
- Multi-tier rigging requirements
- Forklift when used as a crane
The scope expands the definition of cranes to include power-operated equipment used for construction work that can hold, lift, lower, and horizontally move a suspended load with or without attachments. Specifically, this brings powered industrial trucks, including all variations of forklifts – including straight mast forklifts, under the rule when used to lift, lower, or horizontally move a suspended load.
Assembly/disassembly work zones for tower cranes are defined as the total area that the crane/equipment and/or components or attachments could reach if there was a collapse during assembly, disassembly or reconfiguration of the tower crane. Access must be controlled in a manner to restrict unauthorized access to the work zone.
Critical lifts are defined as a lift that exceeds 75% of the rated load chart capacity or a lift that requires the use of more than one crane. Critical lift plans requirements are defined under WAC 296-155-53400 (80) and include requirements to identify load information such as load weight, center of gravity and dimensions, the components that could shift during load handling activity (and develop a method for securing), load attachment points, and load orientation requirements. For crane/equipment, identify the crane/equipment, ensure it has sufficient capacity, it is in compliance with 296-155 WAC, Part L, a process is established for set up, erect, install and dismantle of the equipment and that all tests and inspections have been performed. For rigging, establish the rigging plan, ensure the rigging has capacity, consider dynamic effects, adverse environmental conditions, D/d ratio, ensure rigging meets requirements and has the necessary inspections and tests. Additionally, site parameters, support services, load and equipment travel paths, environmental, site control, load control, personnel location, and other factors should be addressed in the lift plan.
Crane Certifiers have a new pathway to achieve accreditation which includes obtaining a nationally recognized crane inspector certification, passing of a written Washington State certifier examination, completing a minimum of 40 hours of crane related training and submitting an application to Washington State. Due to the detail, we have created a separate article about this topic. Please find the link here.
If a crane is damaged, modified, or repairs of a load sustaining/bearing part that affects the safe operation of the crane (other than general maintenance or routine wear item replacement), a Washington State accredited certifier shall determine if the damage, modifications, or repair work is extensive enough to decertify the crane. Additionally, the crane owner must notify Washington State within 24 hours if the crane has contacted an energized power line, any overload, damage, repairs, modifications, or any deficiency that affects the safe operation of the equipment occurs.
Qualification requirements for Operators, Lift Directors, Signal Persons, Assembly/Disassembly Directors, Repair, Inspection, and Maintenance Personnel, and Riggers have all been updated. Due to the details of these changes, we have created a separate article about this topic. Please find the link here.
When any part of a crane is within the working radius of another, including cranes on different job sites, a coordination plan must be developed and implemented. If a load has the potential to swing over an area that the public can enter, the site supervisor must address controlling and limiting public access to the extent allowed by applicable jurisdictions.
For cranes/equipment other than tower cranes being used inside of, or on, multilevel building sites, methods must be used to prevent the equipment from inadvertently moving while handling a load.
The rule defines the roles and duties of an A/D Director, Certified Crane/Equipment Inspector, Crane Owner, Crane User, Lift Director, Operator, Prime Contractor, Rigger, Signal Person and Site Supervisor.
For power line safety, a planning meeting needs to be conducted for the assembly, disassembly, reconfiguration or operation of the equipment that includes the A/D Director (when applicable), operator, crew, and other workers who will be in the area. The utility owner shall be invited to attend. The meeting needs to be documented and include the names and signatures of all meeting attendees as well as the planning information.
Your Questions Answered
Where can I find more information about this?
Please click here to view the rule.
How do I become a Washington State Accredited Crane Certifier?
You must submit the Application for Accreditation to the Washington Department of Labor and Industries; have a crane inspector certification from a nationally accredited organization such as CCO Certification; successfully pass the Washington state certifier examination; and submit proof of completion of a minimum of 40 hours of crane-related training. Full details are available on Washington L&I’s website, click here for more information.
Are straight mast forklifts included in the construction crane rule for Washington State?
Yes. When they are used to lift, lower, or horizontally move a suspended load
What is the duration of a CCO Certification for crane inspector?
The certification is valid for 5 years
Are forklift operators required to be certified?
Yes – if used to lift or lower a suspended load by means of a hook/shackle. However, if used to lift or lower a suspended load by any other manner, the operator can be either qualified or certified.
Are there requirements for elements of a critical lift plan?
Yes. Requirements include information about the load, crane/equipment, rigging and other impacts. Details are found in WAC 296-155-53400 (80).
What are the duties of assigned personnel?
In the new rule, the roles of A/D Director, Certified Crane/Equipment Inspector, Crane Owner, Crane User, Lift Director, Operator, Prime Contractor, Rigger, Signal Person and Site Supervisor have all been defined as well as their duties and responsibilities. See WAC 296-155-53300 through 53306.
Are there requirements for equipment with capacities under 2,000#?
Yes. Operations inside or on a multi-level building require adequate support and fastening to prevent overturning. Additionally, qualified riggers, lift director and operator evaluations are required.
Who do I contact if I have more questions?